Citizens, worker time and parallel builds
Every upgrade occupies citizens. Worker-days are time × citizens; the parallel estimate is max(worker-days ÷ builders, the longest single chain), not a promise of a schedule.
The two formulas
Each building level lists a build time and a number of citizens it occupies. Multiply them and you get worker-days:
Worker-days = Σ (upgrade time in days × citizens required)
If you have several builders, the earliest possible finish is the larger of two numbers:
Parallel estimate = max(worker-days ÷ available builders, longest single chain)
The second part matters: one building's levels cannot be built at the same time, so a 22.5-day upgrade does not become one day just because you have 30 builders.
Worked example
The Town Center's last level takes 1,944,000 seconds = 22.5 days and occupies 4 citizens.
- Worker-days =
22.5 × 4 = 90. - With 30 builders, the division gives
90 ÷ 30 = 3 days. - The upgrade itself still takes 22.5 days, so the parallel estimate is
max(3, 22.5) = 22.5 days.
Now take ten Farm upgrades at 5 days × 4 citizens each:
- Worker-days =
10 × 5 × 4 = 200. - With 30 builders:
200 ÷ 30 = 6.67 days. - The longest single chain is 5 days, so the estimate is
max(6.67, 5) = 6.67 days.
The first case is limited by one long chain; the second is limited by the total work spread across builders.
Scope
- The planner adds worker-days across the items you selected, not across the whole game.
- The builder count is an input. The estimate is a lower bound: it assumes every builder can work on every selected item and that no resource runs out.
- Citizens used by an upgrade are unavailable for other work until it finishes.
- The game may show a different schedule because of queue order, resources, or bonuses the model does not know.
What is not confirmed
- Whether every building uses the same citizen count while upgrading and while operating.
- How event or research reductions change the occupied citizens, if at all.
- Whether the builder count can exceed the citizens shown on the building.
- Current-server behavior and any queue rules outside the data.